Judge signals hesitance to shut down pipeline, pleads with Wisconsin tribe to work with oil company

FILE - Pipeline used to carry crude oil sits at the Superior, Wis., terminal of Enbridge Energy, June 29, 2018. Attorneys for a Wisconsin Native American tribe are set to argue Thursday, May 18, 2023, that a federal judge should order an energy company to shut down an oil pipeline the tribe says is at immediate risk of being exposed by erosion and rupturing on reservation land. (AP Photo/Jim Mone, File)

MADISON, Wis. (AP) — A federal judge signaled Thursday he will not force an energy company to shut down an oil pipeline in northern Wisconsin, despite arguments from a Native American tribe that the line is at immediate risk of being exposed by erosion and rupturing on reservation land.

The Bad River Band of Lake Superior Chippewa asked U.S. District Judge William Conley last week to issue an emergency ruling forcing Enbridge to shut down the Line 5 pipeline after large chunks of riverbank running alongside it were washed away.

But Conley voiced frustration with the tribe at Thursday’s hearing for not allowing Enbridge to reinforce the land around the pipeline.

“The band has not helped itself by refusing to take any steps to prevent a catastrophic failure at the meander,” Conley said. “You haven’t even allowed simple steps that would have prevented some of this erosion.”

The tribe says less than 15 feet (4.6 meters) of land now stands between the Bad River and Line 5 along a meander on the reservation. In some places, more than 20 feet (6 meters) of riverbank has eroded in the past month alone. Experts and environmental advocates have warned in court that an exposed section of pipeline would be weakened and could rupture at any time, causing massive oil spills.

Conley said before testimony began that it might be necessary for him to order a shutdown at some point, but he was not convinced it was the only option left on Thursday.

Enbridge has repeatedly asked the tribe for permission to place sandbags along the riverbank to prevent erosion. It also requested a permit Monday to install barricades made of trees to protect the pipeline.

Tribal officials have not approved any of the company’s requests.

Judge Conley said the tribe’s inaction undermined claims it has made time and again that the pipeline must be shut down.

“It looks like a strategy, even if it’s just idiocy,” he said. “I’m begging the band to just act. Do something to show you’re acting in good faith.”

The Bad River tribe sued Enbridge in 2019 to force the company to remove the roughly 12-mile (19-kilometer) section of Line 5 that crosses tribal lands, saying the 70-year-old pipeline is dangerous and that land agreements allowing Enbridge to operate on the reservation expired in 2013.

Conley sided with the tribe last September, saying Enbridge was trespassing on the reservation and must compensate the tribe for illegally using its land. But he would not order Enbridge to remove the pipeline due to concerns about what a shutdown might do to the economy of the Great Lakes region.

Instead, Conley told Enbridge and tribal leaders last November to create an emergency shutoff plan for the pipeline. His ruling said there was a significant risk it could burst and cause “catastrophic” damage to the reservation and its water supply.

Line 5 transports up to 23 million gallons (about 87 million liters) of oil and liquid natural gas each day and stretches 645 miles (1,038 kilometers) from the city of Superior through northern Wisconsin and Michigan to Sarnia, Ontario. If the pipeline were shut down, gas prices would likely increase, refineries would shut down, workers would be laid off and the upper Midwest could see years of propane shortages, according to reports Enbridge submitted in court.

Enbridge has proposed a 41-mile (66-kilometer) reroute of the pipeline to end its dispute with the tribe and said in court filings that the project would take less than six years to complete. But the Department of Natural Resources has not granted the permits Enbridge needs to begin construction. A draft analysis of the project’s environmental impact submitted in December 2021 received thousands of public comments, with many criticizing the report as insufficient. The company is still responding to the DNR’s requests for more information.

Line 5 has also faced resistance in Michigan, where Enbridge wants to drill a new tunnel under a strait connecting two of the Great Lakes but Michigan Gov. Gretchen Whitmer and Attorney General Dana Nessel have sought to shut down the pipeline. Nessel filed a brief Wednesday in support of the tribe’s request, saying a rupture in Wisconsin would also cause irreparable environmental damage in Michigan.

___

Harm Venhuizen is a corps member for the Associated Press/Report for America Statehouse News Initiative. Report for America is a nonprofit national service program that places journalists in local newsrooms to report on undercovered issues. Follow Harm on Twitter.